PERMIT #7078804-CN

321 MERCER ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
September 22, 2025
In Review
3 cycles
Reviews Done
December 17, 2025
Ready to Issue
December 17, 2025
Issued
December 17, 2025
Completed
June 26, 2026
Expires
June 17, 2027
86
Plan Review Days — Total
25
Plan Review Days — City Control
61
Days in Applicant Control
3
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$70,000
Type
Commercial Construction
Issued
December 17, 2025
Location
Other Seattle

Contractor Information

Contractor
STERLING Telecom & Const Inc
General Contractor
License STERLTC884C9

Location & Map

Project Description
Verizon EXPO DAS Node 9 Replace light pole with new light pole with telecommunications equipment (Verizon) at Seattle Center, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
STERLTC884C9
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0335960
Related land-use permit
3042816-LU
Review cycles
3
Plan review days
86
Days in corrections
61
Expires
June 17, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →