PERMIT #7081074-CN
6527 53RD AVE NE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
November 10, 2025
In Review
3 cycles
Reviews Done
February 13, 2026
Ready to Issue
February 13, 2026
Issued
June 16, 2026
Completed
—
Expires
—
95
Plan Review Days — Total
42
Plan Review Days — City Control
53
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
6527 53RD AVE NE, SEATTLE, WA Property
Demolition at 6527 53RD AVE NE Project
Laurelhurst Neighborhood
Project Overview
Project Details
Value
$561,104
Type
Residential Construction
Issued
June 16, 2026
Location
Laurelhurst
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Establish use as single-family residence per land use code. Construct one-family dwelling per plan.
Additional Details
Permit Intelligence
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1124471
Review cycles
3
Plan review days
95
Days in corrections
53
Units added
1
Units removed
1