PERMIT #7081976-CN

8349 20TH AVE NW, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
April 22, 2025
In Review
Issued
April 23, 2025
Completed
February 9, 2026
Expires
October 23, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$100,000
Type
Residential Construction
Issued
April 23, 2025
Location
Ballard

Contractor Information

Contractor
HARDING FERRARIO CONST LLC
General Contractor
License HARDIFC839PC

Location & Map

Project Description
Basement renovation Construct alterations throughout one-family dwelling, subject to field inspection (STFI)

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
HARDIFC839PC
Review level
Field
Primary use
Single Family/Duplex
Parcel
DV0079070
Expires
October 23, 2026
Existing units
1
Sleeping rooms
2
Open official SDCI detail →
View Contractor