PERMIT #7082421-CN
325 9TH AVE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 4, 2025
In Review
2 cycles
Reviews Done
February 2, 2026
Ready to Issue
February 3, 2026
Issued
February 4, 2026
Completed
—
Expires
August 4, 2027
60
Plan Review Days — Total
54
Plan Review Days — City Control
6
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$4,000,000
Type
Commercial Construction
Issued
February 4, 2026
Location
First Hill
Contractor Information
Location & Map
Project Description
325 9th Ave - Construction Permit Construct alterations and install diagnostic equipment at ground level lab of institutional building [HARBORVIEW MEDICAL CENTER], per plan. Mechanical included.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BNBUII*990K3
Review level
Full C
Primary use
Institutional
Parcel
DV0065890
Review cycles
2
Plan review days
60
Days in corrections
6
Expires
August 4, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0