PERMIT #7083054-CN
311 HOWE ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
November 4, 2025
In Review
3 cycles
Reviews Done
February 19, 2026
Ready to Issue
February 24, 2026
Issued
March 2, 2026
Completed
—
Expires
September 2, 2027
107
Plan Review Days — Total
38
Plan Review Days — City Control
69
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
311 HOWE ST, SEATTLE, WA Property
Addition at 311 HOWE ST Project
SUNDQUIST ENTERPRISES LLC Contractor
Queen Anne Neighborhood
Project Overview
Project Details
Value
$323,225
Type
Residential Construction
Issued
March 2, 2026
Location
Queen Anne
Contractor Information
Location & Map
Project Description
Muska Remodel Construct addition and substantial alterations to one-family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SUNDQEL774PW
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0077927
Review cycles
3
Plan review days
107
Days in corrections
69
Expires
September 2, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
3