PERMIT #7084189-CN

6044 49th AVE SW, Seattle, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
May 6, 2025
In Review
Issued
May 14, 2025
Completed
October 30, 2025
Expires
November 14, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
West Seattle Neighborhood

Project Overview

Project Details
Value
$80,000
Type
Residential Construction
Issued
May 14, 2025
Location
West Seattle

Contractor Information

Contractor
E&G ALL IN ONE CONST LLC
General Contractor
License EGALLAO753BT

Location & Map

Project Description
Griesser addition Construct office and bedroom addition at main floor of existing one-family dwelling, subject to field inspection (STFI).

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
EGALLAO753BT
Review level
Field
Primary use
Single Family/Duplex
Parcel
DV0027338
Expires
November 14, 2026