PERMIT #7084885-CN
426 TERRY AVE N, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
June 4, 2025
In Review
—
Issued
October 3, 2025
Completed
April 27, 2026
Expires
April 3, 2027
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$200,000
Type
Commercial Construction
Issued
October 3, 2025
Location
South Lake Union
Contractor Information
Location & Map
Project Description
426 Terry Ave N - Construction - 321_P603902 Tenant improvement for new security gates at freight elevators, Levels P2, P3, & PA, of existing commercial building, per plan
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SWINEB*992DR
Review level
Full +
Primary use
Commercial
Parcel
DV0011929
Expires
April 3, 2027
Existing units
0
Sleeping rooms
0