PERMIT #7085537-CN
515 WESTLAKE AVE N, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
May 13, 2025
In Review
—
Issued
May 15, 2025
Completed
January 15, 2026
Expires
November 15, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
515 WESTLAKE AVE N, SEATTLE, WA Property
CORTI CONSTRUCTION INC Contractor
South Lake Union Neighborhood
Project Overview
Project Details
Value
$180,000
Type
Commercial Construction
Issued
May 15, 2025
Location
South Lake Union
Contractor Information
Location & Map
Project Description
339_P541103 Construct tenant improvements for office space at levels 2 - 5 of existing commercial building, subject to field inspection (STFI)
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
CORTICI838JO
Review level
Field
Primary use
Commercial
Parcel
DV0079356
Expires
November 15, 2026