PERMIT #7086005-CN
3928 S GRAHAM ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
August 19, 2025
In Review
3 cycles
Issued
January 8, 2026
Completed
—
Expires
July 8, 2027
139
Plan Review Days — Total
74
Plan Review Days — City Control
65
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
3928 S GRAHAM ST, SEATTLE, WA Property
Demolition at 3928 S GRAHAM ST Project
LYDIG CONSTRUCTION INC Contractor
Hillman City Neighborhood
Project Overview
Project Details
Value
$5,600,000
Type
Commercial Construction
Issued
January 8, 2026
Location
Hillman City
Contractor Information
Location & Map
Project Description
Aki Kurose Middle School Construct geothermal drilling and site work for Aki Kurose middle school, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
LYDIGC*264JC
Review level
Full +
Primary use
Institutional
Parcel
DV0002049
Review cycles
3
Plan review days
139
Days in corrections
65
Expires
July 8, 2027