PERMIT #7088096-CN
5214 S WILLOW ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 2, 2025
In Review
5 cycles
Issued
May 20, 2026
Completed
—
Expires
November 20, 2027
204
Plan Review Days — Total
144
Plan Review Days — City Control
60
Days in Applicant Control
5
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
5214 S WILLOW ST, SEATTLE, WA Property
Seward Park Neighborhood
Project Overview
Project Details
Value
$353,955
Type
Residential Construction
Issued
May 20, 2026
Location
Seward Park
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Construction Permit - East One Family Construct east one-family dwelling, per plan. (Establish use as single-family dwelling units, per Land Use Code. Construct 3 one-family dwellings per plan. Review and process for 3 records under 7088096-CN)
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV0362000
Review cycles
5
Plan review days
204
Days in corrections
60
Expires
November 20, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0