PERMIT #7088830-CN

800 5TH AVE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 25, 2025
In Review
2 cycles
Reviews Done
January 14, 2026
Ready to Issue
January 15, 2026
Issued
January 15, 2026
Completed
Expires
July 15, 2027
50
Plan Review Days — Total
45
Plan Review Days — City Control
5
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Downtown Neighborhood

Project Overview

Project Details
Value
$863,131
Type
Commercial Construction
Issued
January 15, 2026
Location
Downtown

Contractor Information

Contractor
SKYLINE CONSTRUCTION
Commercial
License SKYLIC*773DW

Location & Map

Project Description
Casey Family Foundation Construct tenant improvements for office spaces on floors 39-42 of existing commercial building, occupy per plan

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SKYLIC*773DW
Housing category
Commercial Add/Alt
Review level
Full C
Primary use
Commercial
Parcel
DV0029701
Review cycles
2
Plan review days
50
Days in corrections
5
Expires
July 15, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor