PERMIT #7089209-DM
3266 37TH AVE SW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 4, 2025
In Review
1 cycle
Reviews Done
December 26, 2025
Ready to Issue
January 13, 2026
Issued
January 14, 2026
Completed
—
Expires
July 14, 2027
22
Plan Review Days — Total
22
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
3266 37TH AVE SW, SEATTLE, WA Property
Demolition at 3266 37TH AVE SW Project
West Seattle Neighborhood
Project Overview
Project Details
Value
$434,875
Type
Residential Construction
Issued
January 14, 2026
Location
West Seattle
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Rebuild SFR, Existing footings to remain Demolish existing one family dwelling, existing foundation to remain, per plan.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1109602
Review cycles
1
Plan review days
22
Days in corrections
0
Expires
July 14, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
3