PERMIT #7089221-CN

6827 49TH AVE NE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
October 13, 2025
In Review
2 cycles
Reviews Done
February 12, 2026
Ready to Issue
February 12, 2026
Issued
February 12, 2026
Completed
Expires
August 12, 2027
122
Plan Review Days — Total
41
Plan Review Days — City Control
81
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Laurelhurst Neighborhood

Project Overview

Project Details
Value
$116,581
Type
Residential Construction
Issued
February 12, 2026
Location
Laurelhurst

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Park Perrins Construct alterations and 2-story addition to existing one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Other Exemption from RCW 18.27.090
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0034746
Review cycles
2
Plan review days
122
Days in corrections
81
Expires
August 12, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
Open Map