Permit Timeline & Status

Construction Permit Timeline
Applied
April 21, 2026
In Review
1 cycle
Issued
Completed
Expires
74
Days in Applicant Control
1
Review Cycles
Next stepIn City review — awaiting the next action.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Maple Leaf Neighborhood

Project Overview

Project Details
Value
$222,058
Type
Residential Construction
Issued
N/A
Location
Maple Leaf

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
Ditos Daranciang Allow housing for detached dwelling unit, per land use code. Existing detached dwelling to remain. Construct new one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0048039
Review cycles
1
Days in corrections
74