PERMIT #7089650-CN
7128 30TH AVE SW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 5, 2025
In Review
2 cycles
Issued
October 14, 2025
Completed
—
Expires
April 14, 2027
38
Plan Review Days — Total
33
Plan Review Days — City Control
5
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$75,000
Type
Residential Construction
Issued
October 14, 2025
Location
West Seattle
Contractor Information
Location & Map
Project Description
Dempsey-Hall AADU Allow new attached accessory dwelling unit to existing single family use per land use code. Construct alterations for a two family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
ONIXCCL791QA
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0020054
Review cycles
2
Plan review days
38
Days in corrections
5
Expires
April 14, 2027
Existing units
1
Units added
1
Units removed
0
Sleeping rooms
0