PERMIT #7089776-CN
1022 ALASKAN WAY, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 20, 2025
In Review
3 cycles
Reviews Done
February 25, 2026
Ready to Issue
February 26, 2026
Issued
February 26, 2026
Completed
—
Expires
August 26, 2027
128
Plan Review Days — Total
51
Plan Review Days — City Control
77
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$1,750,000
Type
Commercial Construction
Issued
February 26, 2026
Location
Downtown
Contractor Information
Location & Map
Project Description
Daria Supp Establish use as eating and drinking establishment per the Land Use Code. Construct tenant improvements, covered exterior dining, and site improvements for bar (Urban Family Brewing) at first floor of existing mixed-use building, occupy per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
RYANGCI930PC
Housing category
Commercial Add/Alt
Review level
Full C
Primary use
Commercial
Parcel
DV0013398
Review cycles
3
Plan review days
128
Days in corrections
77
Expires
August 26, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0