PERMIT #7090229-CN

450 3RD AVE W, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
June 9, 2025
In Review
Issued
June 23, 2025
Completed
October 28, 2025
Expires
December 23, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$455,176
Type
Commercial Construction
Issued
June 23, 2025
Location
Other Seattle

Contractor Information

Contractor
AVARA CONSTRUCTION INC
General Contractor
License AVARACI824BR

Location & Map

Project Description
450 3rd Ave W - Construction Construct tenant improvements at portions of 3rd and 4th level tenant spaces [HOLLAND AMERICA] in commercial office building [THIRD & HARRISON BUILDING], subject to field inspection [STFI].

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
AVARACI824BR
Review level
Field
Primary use
Commercial
Parcel
DV0083517
Expires
December 23, 2026