PERMIT #7090862-CN

1515 ALASKAN WAY, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
August 19, 2025
In Review
2 cycles
Issued
September 11, 2025
Completed
February 6, 2026
Expires
March 11, 2027
23
Plan Review Days — Total
17
Plan Review Days — City Control
6
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Downtown Neighborhood

Project Overview

Project Details
Value
$250,000
Type
Commercial Construction
Issued
September 11, 2025
Location
Downtown

Contractor Information

Contractor
AS CONTRACTOR LLC
General Contractor
License ASCONCL805MO

Location & Map

Project Description
Overlook Walk Pavilion - Boon Boona Coffee Construct initial tenant improvement to existing assembly building for a restaurant, occupy per plans. Mechanical included this permit.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
ASCONCL805MO
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0090213
Review cycles
2
Plan review days
23
Days in corrections
6
Expires
March 11, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor