PERMIT #7091370-CN
501 FAIRVIEW AVE N, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
June 16, 2025
In Review
—
Issued
June 19, 2025
Completed
October 20, 2025
Expires
December 19, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
501 FAIRVIEW AVE N, SEATTLE, WA Property
CORTI CONSTRUCTION INC Contractor
South Lake Union Neighborhood
Project Overview
Project Details
Value
$160,000
Type
Commercial Construction
Issued
June 19, 2025
Location
South Lake Union
Contractor Information
Location & Map
Project Description
352_P572010 Tenant improvements to install booths on floors 3,4,5,10,11 and 12 of existing office building, subject to field inspection.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
CORTICI838JO
Review level
Field
Primary use
Commercial
Parcel
DV0079378
Expires
December 19, 2026