PERMIT #7093037-CN

2832 SW NEVADA ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 17, 2025
In Review
5 cycles
Reviews Done
July 27, 2026
Ready to Issue
July 27, 2026
Issued
July 28, 2026
Completed
Expires
252
Plan Review Days — Total
98
Plan Review Days — City Control
154
Days in Applicant Control
5
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$713,647
Type
Residential Construction
Issued
July 28, 2026
Location
West Seattle

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct north two-family dwelling per plan. (Establish use as townhouses per land use code. Construct (2) two-family dwellings per plan. Review and processing for two records under 7093037-CN)

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV0363060
Review cycles
5
Plan review days
252
Days in corrections
154
Units added
2
Units removed
0
Open Map