PERMIT #7093585-CN

7709 SEWARD PARK AVE S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 19, 2025
In Review
2 cycles
Reviews Done
February 13, 2026
Ready to Issue
February 17, 2026
Issued
February 17, 2026
Completed
Expires
August 17, 2027
86
Plan Review Days — Total
84
Plan Review Days — City Control
2
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$486,776
Type
Residential Construction
Issued
February 17, 2026
Location
Rainier Beach

Contractor Information

Contractor
HERNANDEZ BUILDS LLC
General Contractor
License HERNABL805RC

Location & Map

Project Description
Construction Permit Construct SOUTHWEST one-family dwelling (Unit A), per plan. (Establish use as single-family dwelling units, per Land Use Code. Construct (4) one-family dwellings, per plan. Review and processing for (4) records under 7093585-CN.)

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
HERNABL805RC
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1219012
Review cycles
2
Plan review days
86
Days in corrections
2
Expires
August 17, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor