PERMIT #7093668-CN
1221 E PIKE ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 8, 2025
In Review
2 cycles
Reviews Done
January 5, 2026
Ready to Issue
January 8, 2026
Issued
January 8, 2026
Completed
—
Expires
July 8, 2027
89
Plan Review Days — Total
78
Plan Review Days — City Control
11
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1221 E PIKE ST, SEATTLE, WA Property
Renovation at 1221 E PIKE ST Project
BELOTTI MCHUGH DSN\CNST SR LLC Contractor
Capitol Hill Neighborhood
Project Overview
Project Details
Value
$200,000
Type
Commercial Construction
Issued
January 8, 2026
Location
Capitol Hill
Contractor Information
Location & Map
Project Description
1221 E Pike St - Construction - Elysian Brewing Co Renovation Construct alterations to restaurant/brewery [ELYSIAN BREWING CO] at ground level of mixed-use commercial building, occupy per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BELOTMD881CG
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0039402
Review cycles
2
Plan review days
89
Days in corrections
11
Expires
July 8, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0