PERMIT #7094482-CN
305 HARRISON ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 2, 2025
In Review
3 cycles
Reviews Done
April 29, 2026
Ready to Issue
April 29, 2026
Issued
May 1, 2026
Completed
—
Expires
November 1, 2027
148
Plan Review Days — Total
120
Plan Review Days — City Control
28
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
305 HARRISON ST, SEATTLE, WA Property
Belltown Neighborhood
Project Overview
Project Details
Value
$2,000,000
Type
Commercial Construction
Issued
May 1, 2026
Location
Belltown
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Armory Generator and Renewables Construct addition and alterations to institutional building (The Armory emergency generator, vault, and renewable energy improvements), per plan. Mechanical included.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Commercial Add/Alt
Review level
Full C
Primary use
Commercial
Parcel
DV1199717
Review cycles
3
Plan review days
148
Days in corrections
28
Expires
November 1, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0