PERMIT #7094617-CN

5621 22ND AVE NW, SEATTLE, WA

new

Permit Timeline & Status

Construction Permit Timeline
Applied
January 5, 2026
In Review
3 cycles
Reviews Done
June 9, 2026
Ready to Issue
July 24, 2026
Issued
Completed
Expires
155
Plan Review Days — Total
103
Plan Review Days — City Control
52
Days in Applicant Control
3
Review Cycles
Next stepPlan review complete — ready to issue, awaiting final fees/issuance.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Ballard Neighborhood

Project Overview

Project Details
Value
$4,000,000
Type
Commercial Construction
Issued
N/A
Location
Ballard

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Change two levels of tower from office to multi-family per the land use code. Construct alterations for same in portion of a mixed-use building occupy per plan. (Mechanical included this permit)

Additional Details

Permit Intelligence
Housing category
Commercial Add/Alt
Review level
Full C
Primary use
Commercial
Parcel
DV0016977
Review cycles
3
Plan review days
155
Days in corrections
52
Units added
23
Units removed
0
Open Map