PERMIT #7095019-CN

8814 B 17TH AVE NE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 17, 2025
In Review
2 cycles
Reviews Done
February 23, 2026
Ready to Issue
March 4, 2026
Issued
March 4, 2026
Completed
Expires
September 4, 2027
98
Plan Review Days — Total
38
Plan Review Days — City Control
60
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$100,000
Type
Residential Construction
Issued
March 4, 2026
Location
Maple Leaf

Contractor Information

Contractor
WESTLAKE BUILDERS LLC
General Contractor
License WESTLBL789DQ

Location & Map

Project Description
Garage to DADU Conversion Allow new detached accessory dwelling unit to existing single-family use, per land use code. . Construct substantial alterations to a detached garage for a one-family dwelling, per plans

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
WESTLBL789DQ
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0362580
Review cycles
2
Plan review days
98
Days in corrections
60
Expires
September 4, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor