PERMIT #7095032-CN
334 W KINNEAR PL, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
August 28, 2025
In Review
3 cycles
Issued
December 23, 2025
Completed
—
Expires
June 23, 2027
116
Plan Review Days — Total
48
Plan Review Days — City Control
68
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
334 W KINNEAR PL, SEATTLE, WA Property
Addition at 334 W KINNEAR PL Project
JAS DESIGN-BUILD INC Contractor
Queen Anne Neighborhood
Project Overview
Project Details
Value
$62,622
Type
Residential Construction
Issued
December 23, 2025
Location
Queen Anne
Contractor Information
Location & Map
Project Description
Keating Reimel Garage Addition and alteration to detatched structure accessory to existing one family dwelling, and site improvements, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
JASDEDI775QN
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0036785
Review cycles
3
Plan review days
116
Days in corrections
68
Expires
June 23, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0