PERMIT #7095078-CN

6046 36TH AVE SW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
September 15, 2025
In Review
3 cycles
Reviews Done
February 18, 2026
Ready to Issue
February 26, 2026
Issued
March 2, 2026
Completed
Expires
September 2, 2027
156
Plan Review Days — Total
86
Plan Review Days — City Control
70
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
West Seattle Neighborhood

Project Overview

Project Details
Value
$729,371
Type
Residential Construction
Issued
March 2, 2026
Location
West Seattle

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
Construction Permit Construct West two-family dwelling, per plan. (Establish use as townhouses per land use code. Construct two-family dwellings, per plan. Review and processing for (2) construction records under 7095078-CN.)

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1117400
Related land-use permit
3043102-LU
Review cycles
3
Plan review days
156
Days in corrections
70
Expires
September 2, 2027
Existing units
0
Units added
2
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
Open Map