PERMIT #7095139-CN

1737 AIRPORT WAY S, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
September 5, 2025
In Review
2 cycles
Reviews Done
October 20, 2025
Ready to Issue
October 21, 2025
Issued
October 21, 2025
Completed
February 25, 2026
Expires
April 21, 2027
45
Plan Review Days — Total
41
Plan Review Days — City Control
4
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
SoDo Neighborhood

Project Overview

Project Details
Value
$502,787
Type
Commercial Construction
Issued
October 21, 2025
Location
SoDo

Contractor Information

Contractor
DAVIS SCHUELLER INC
General Contractor
License DAVISSI105PN

Location & Map

Project Description
Evergreen Treatment Services Tenant Improvements at SE corner of 1st floor of existing commercial building, per plan

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
DAVISSI105PN
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0005114
Review cycles
2
Plan review days
45
Days in corrections
4
Expires
April 21, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor