PERMIT #7095232-CN
2420 2ND AVE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 15, 2025
In Review
2 cycles
Reviews Done
March 29, 2026
Ready to Issue
March 30, 2026
Issued
March 30, 2026
Completed
—
Expires
September 30, 2027
104
Plan Review Days — Total
96
Plan Review Days — City Control
8
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$250,000
Type
Commercial Construction
Issued
March 30, 2026
Location
Belltown
Contractor Information
Location & Map
Project Description
CLC - TI Change of use from office to religious facility, per Land Use Code. Construct alterations to existing office building, occupy per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BLOXCCI955BD
Housing category
Commercial Add/Alt
Review level
Full C
Primary use
Commercial
Parcel
DV0017315
Review cycles
2
Plan review days
104
Days in corrections
8
Expires
September 30, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0