PERMIT #7095249-CN
354 N 79TH ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 24, 2025
In Review
2 cycles
Reviews Done
December 19, 2025
Ready to Issue
December 22, 2025
Issued
December 22, 2025
Completed
—
Expires
June 22, 2027
56
Plan Review Days — Total
40
Plan Review Days — City Control
16
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
354 N 79TH ST, SEATTLE, WA Property
Addition at 354 N 79TH ST Project
CRD DESIGN BUILD INC Contractor
Phinney Ridge Neighborhood
Project Overview
Project Details
Value
$147,533
Type
Residential Construction
Issued
December 22, 2025
Location
Phinney Ridge
Contractor Information
Location & Map
Project Description
354 N 79th St - Construction - Mitchell Harrison Addition Construct alterations and additions for one-family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
CRDDEDB831OL
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0056951
Review cycles
2
Plan review days
56
Days in corrections
16
Expires
June 22, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0