PERMIT #7095487-CN
116 13TH AVE E, Seattle, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
November 9, 2025
In Review
5 cycles
Reviews Done
March 30, 2026
Ready to Issue
April 12, 2026
Issued
April 14, 2026
Completed
—
Expires
October 14, 2027
141
Plan Review Days — Total
202
Days in Applicant Control
5
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$30,000
Type
Residential Construction
Issued
April 14, 2026
Location
Capitol Hill
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Construction Permit Construct alterations to existing boarding house at basement level, per plan.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Multifamily
Parcel
DV0078040
Review cycles
5
Plan review days
141
Days in corrections
202
Expires
October 14, 2027
Existing units
57
Units added
3
Units removed
0
Sleeping rooms
0