PERMIT #7095761-CN
558 S KENYON ST, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
September 30, 2025
In Review
2 cycles
Reviews Done
November 25, 2025
Ready to Issue
December 1, 2025
Issued
December 1, 2025
Completed
March 17, 2026
Expires
June 1, 2027
56
Plan Review Days — Total
15
Plan Review Days — City Control
41
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$62,630
Type
Commercial Construction
Issued
December 1, 2025
Location
South Park
Contractor Information
Location & Map
Project Description
Marine Lumber Racking Install lumber racks in a warehouse building, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MRRACRL924BN
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0002210
Review cycles
2
Plan review days
56
Days in corrections
41
Expires
June 1, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0