PERMIT #7096052-CN
1050 SW SPOKANE ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 10, 2025
In Review
0 cycles
Reviews Done
March 4, 2026
Ready to Issue
March 6, 2026
Issued
April 15, 2026
Completed
—
Expires
October 15, 2027
175
Plan Review Days — Total
175
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1050 SW SPOKANE ST, SEATTLE, WA Property
Renovation at 1050 SW SPOKANE ST Project
West Seattle Neighborhood
Project Overview
Project Details
Value
$11,009,334
Type
Industrial Construction
Issued
April 15, 2026
Location
West Seattle
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
1050 SW Spokane St - Construction and Grading - Terminal 18 Shore Power Construct middle substation and associated power vault and sitework, per plan. [Construct shore power vaults, substations, and associated site alterations for container terminal [PORT OF SEATTLE, TERMINAL 18], per plan. Review and processing for (3) construction records under 7046509-CN.]
Additional Details
Permit Intelligence
Review level
Dependent Building
Primary use
Industrial
Parcel
DV0066407
Review cycles
0
Plan review days
175
Days in corrections
0
Expires
October 15, 2027