PERMIT #7096286-CN

4717 26TH AVE SW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
October 6, 2025
In Review
3 cycles
Reviews Done
March 20, 2026
Ready to Issue
April 1, 2026
Issued
April 1, 2026
Completed
Expires
October 1, 2027
165
Plan Review Days — Total
67
Plan Review Days — City Control
98
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
PLACES Contractor
West Seattle Neighborhood

Project Overview

Project Details
Value
$232,478
Type
Residential Construction
Issued
April 1, 2026
Location
West Seattle

Contractor Information

Contractor
PLACES
General Contractor
License PLACE**760PA

Location & Map

Project Description
New SFR Establish single family residence, per land use code. Construct new one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
PLACE**760PA
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1113979
Review cycles
3
Plan review days
165
Days in corrections
98
Expires
October 1, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor