PERMIT #7096286-CN
4717 26TH AVE SW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 6, 2025
In Review
3 cycles
Reviews Done
March 20, 2026
Ready to Issue
April 1, 2026
Issued
April 1, 2026
Completed
—
Expires
October 1, 2027
165
Plan Review Days — Total
67
Plan Review Days — City Control
98
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$232,478
Type
Residential Construction
Issued
April 1, 2026
Location
West Seattle
Contractor Information
Location & Map
Project Description
New SFR Establish single family residence, per land use code. Construct new one family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
PLACE**760PA
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1113979
Review cycles
3
Plan review days
165
Days in corrections
98
Expires
October 1, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0