PERMIT #7096287-CN

10861 ARROYO BEACH PL SW, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
September 3, 2025
In Review
2 cycles
Issued
December 8, 2025
Completed
March 9, 2026
Expires
June 8, 2027
93
Plan Review Days — Total
63
Plan Review Days — City Control
30
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$20,000
Type
Residential Construction
Issued
December 8, 2025
Location
Other Seattle

Contractor Information

Contractor
GROUNDWORKS
General Contractor
License GROUN**763O5

Location & Map

Project Description
Komanapalli Foundation Repair Underpin foundation at the southeast corner of existing one-family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GROUN**763O5
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0053464
Review cycles
2
Plan review days
93
Days in corrections
30
Expires
June 8, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor