PERMIT #7096543-CN

2970 SW AVALON WAY, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
October 2, 2025
In Review
2 cycles
Reviews Done
January 16, 2026
Ready to Issue
January 20, 2026
Issued
January 20, 2026
Completed
Expires
July 20, 2027
106
Plan Review Days — Total
30
Plan Review Days — City Control
76
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
ACHomes LLC Contractor
West Seattle Neighborhood

Project Overview

Project Details
Value
$236,720
Type
Commercial Construction
Issued
January 20, 2026
Location
West Seattle

Contractor Information

Contractor
ACHomes LLC
General Contractor
License ACHOML*864NK

Location & Map

Project Description
2970 Addition Construct alterations and addition to existing group home (Transitional Resources), per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
ACHOML*864NK
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0004709
Review cycles
2
Plan review days
106
Days in corrections
76
Expires
July 20, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor