PERMIT #7096728-CN

5959 CORSON AVE S, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
August 26, 2025
In Review
2 cycles
Issued
October 1, 2025
Completed
January 26, 2026
Expires
April 1, 2027
35
Plan Review Days — Total
20
Plan Review Days — City Control
15
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$240,000
Type
Commercial Construction
Issued
October 1, 2025
Location
Georgetown

Contractor Information

Contractor
BOYCE CONSTRUCTION INC
General Contractor
License BOYCECI066QQ

Location & Map

Project Description
Georgetown Center C-W T.I. Construct alterations building to create new tenant space in existing mixed-use building, occupy per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BOYCECI066QQ
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0004774
Review cycles
2
Plan review days
35
Days in corrections
15
Expires
April 1, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor