PERMIT #7096922-CN

325 EASTLAKE AVE E, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
July 18, 2025
In Review
Issued
July 21, 2025
Completed
December 9, 2025
Expires
January 21, 2027
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$60,000
Type
Commercial Construction
Issued
July 21, 2025
Location
South Lake Union

Contractor Information

Contractor
CORTI CONSTRUCTION INC
General Contractor
License CORTICI838JO

Location & Map

Project Description
361_P573202 Construct alterations to install 51"inch by 92.6" inch by 91/7"inch tall premanufactured phone booths within existing office space, per plot plan and subject to field inspection (STFI)

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
CORTICI838JO
Review level
Field
Primary use
Commercial
Parcel
DV0338681
Expires
January 21, 2027
Open official SDCI detail →