PERMIT #7097066-CN
1124 LAKEVIEW BLVD E, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
November 14, 2025
In Review
4 cycles
Reviews Done
January 21, 2026
Ready to Issue
January 26, 2026
Issued
January 26, 2026
Completed
—
Expires
July 26, 2027
68
Plan Review Days — Total
51
Plan Review Days — City Control
17
Days in Applicant Control
4
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1124 LAKEVIEW BLVD E, SEATTLE, WA Property
Capitol Hill Neighborhood
Project Overview
Project Details
Value
$50,000
Type
Residential Construction
Issued
January 26, 2026
Location
Capitol Hill
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Construction Permit Allow one attached accessory dwelling unit subordinate to existing apartment (multifamily residential), per land use code. Add one unit to existing multifamily building, occupy per plan.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Multifamily
Parcel
DV0034455
Review cycles
4
Plan review days
68
Days in corrections
17
Expires
July 26, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0