PERMIT #7097163-CN
3236 34TH AVE W, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 7, 2025
In Review
2 cycles
Reviews Done
February 18, 2026
Ready to Issue
February 23, 2026
Issued
March 23, 2026
Completed
—
Expires
September 23, 2027
134
Plan Review Days — Total
93
Plan Review Days — City Control
41
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
3236 34TH AVE W, SEATTLE, WA Property
Demolition at 3236 34TH AVE W Project
MOKAN HOMES LLC Contractor
Magnolia Neighborhood
Project Overview
Project Details
Value
$794,811
Type
Residential Construction
Issued
March 23, 2026
Location
Magnolia
Contractor Information
Location & Map
Project Description
PK 34TH HOMES Construct WEST new two-family dwelling (BLDG A) and site improvements, per plan. (Establish use as two single family residences, per Land Use Code. Construct two new two-family dwellings, per plan. Review and processing for two records under 7097163-CN.)
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MOKANHL813BG
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1117272
Related land-use permit
3044059-LU
Review cycles
2
Plan review days
134
Days in corrections
41
Expires
September 23, 2027
Existing units
2
Units added
2
Units removed
0
Sleeping rooms
0