PERMIT #7097333-CN

810 B N 59TH ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
August 28, 2025
In Review
4 cycles
Issued
February 10, 2026
Completed
Expires
August 10, 2027
162
Plan Review Days — Total
289
Days in Applicant Control
4
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$565,186
Type
Residential Construction
Issued
February 10, 2026
Location
Green Lake

Contractor Information

Contractor
ALL INCLUSIVE HOME DESIGN LLC
General Contractor
License ALLINIH848QH

Location & Map

Project Description
810 N 59th St - Construction permit Allow attached accessory dwelling unit to existing single-family use, per land use code. Construct substantial alterations and additions and convert one-family dwelling to two-family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
ALLINIH848QH
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1202962
Review cycles
4
Plan review days
162
Days in corrections
289
Expires
August 10, 2027