PERMIT #7097338-CN
2700 W COMMODORE WAY, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 5, 2025
In Review
2 cycles
Reviews Done
November 25, 2025
Ready to Issue
December 4, 2025
Issued
December 4, 2025
Completed
—
Expires
June 4, 2027
81
Plan Review Days — Total
227
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
2700 W COMMODORE WAY, SEATTLE, WA Property
MIDMOUNTAIN CONTRACTORS INC Contractor
Magnolia Neighborhood
Project Overview
Project Details
Value
$4,600,000
Type
Industrial Construction
Issued
December 4, 2025
Location
Magnolia
Contractor Information
Location & Map
Project Description
MIC Elec Infrastructure Replacement Construct new switch gear enclosures for existing commercial complex (Maritime Industrial Center), per plan
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MIDMOCI972OB
Review level
Full +
Primary use
Industrial
Parcel
DV0008023
Review cycles
2
Plan review days
81
Days in corrections
227
Expires
June 4, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0