PERMIT #7097339-DM

2700 W COMMODORE WAY, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
October 3, 2025
In Review
2 cycles
Reviews Done
January 26, 2026
Ready to Issue
January 29, 2026
Issued
January 29, 2026
Completed
May 15, 2026
Expires
July 29, 2027
115
Plan Review Days — Total
38
Plan Review Days — City Control
77
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$4,600,000
Type
Industrial Construction
Issued
January 29, 2026
Location
Magnolia

Contractor Information

Contractor
MIDMOUNTAIN CONTRACTORS INC
General Contractor
License MIDMOCI972OB

Location & Map

Project Description
MIC Elec Infrastructure Replacement Demolish existing shed and switchgear enclosure in existing commercial complex (Maritime Industrial Center), per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MIDMOCI972OB
Review level
Full +
Primary use
Industrial
Parcel
DV0008023
Review cycles
2
Plan review days
115
Days in corrections
77
Expires
July 29, 2027
Open official SDCI detail →