PERMIT #7097339-DM
2700 W COMMODORE WAY, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
October 3, 2025
In Review
2 cycles
Reviews Done
January 26, 2026
Ready to Issue
January 29, 2026
Issued
January 29, 2026
Completed
May 15, 2026
Expires
July 29, 2027
115
Plan Review Days — Total
38
Plan Review Days — City Control
77
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
2700 W COMMODORE WAY, SEATTLE, WA Property
MIDMOUNTAIN CONTRACTORS INC Contractor
Magnolia Neighborhood
Project Overview
Project Details
Value
$4,600,000
Type
Industrial Construction
Issued
January 29, 2026
Location
Magnolia
Contractor Information
Location & Map
Project Description
MIC Elec Infrastructure Replacement Demolish existing shed and switchgear enclosure in existing commercial complex (Maritime Industrial Center), per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MIDMOCI972OB
Review level
Full +
Primary use
Industrial
Parcel
DV0008023
Review cycles
2
Plan review days
115
Days in corrections
77
Expires
July 29, 2027