PERMIT #7097345-CN
13739 23RD AVE NE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 10, 2025
In Review
3 cycles
Reviews Done
February 2, 2026
Ready to Issue
February 3, 2026
Issued
February 3, 2026
Completed
—
Expires
August 3, 2027
115
Plan Review Days — Total
115
Plan Review Days — City Control
0
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
13739 23RD AVE NE, SEATTLE, WA Property
Demolition at 13739 23RD AVE NE Project
Pinehurst Neighborhood
Project Overview
Project Details
Value
$297,334
Type
Residential Construction
Issued
February 3, 2026
Location
Pinehurst
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Construction Permit Construct new East one family dwelling (SFR1), per plan. (Establish use as single family residence per land use code. Construct 3 new one family dwellings, per plan. Review and process for 3 records under 7097345-CN)
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1143776
Review cycles
3
Plan review days
115
Days in corrections
0
Expires
August 3, 2027
Existing units
1
Units added
1
Units removed
0
Sleeping rooms
0