PERMIT #7097435-CN
4529 51ST PL SW, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
August 8, 2025
In Review
—
Issued
October 29, 2025
Completed
April 7, 2026
Expires
April 29, 2027
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
4529 51ST PL SW, SEATTLE, WA Property
Renovation at 4529 51ST PL SW Project
GROUNDWORKS Contractor
West Seattle Neighborhood
Project Overview
Project Details
Value
$62,000
Type
Residential Construction
Issued
October 29, 2025
Location
West Seattle
Contractor Information
Location & Map
Project Description
McLaughlin Foundation Repair Construct alterations to install push pier supports for existing residential foundation, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GROUN**763O5
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1166879
Expires
April 29, 2027
Existing units
1
Sleeping rooms
0