PERMIT #7097729-CN

2112 N 52ND ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 23, 2025
In Review
3 cycles
Reviews Done
April 8, 2026
Ready to Issue
April 9, 2026
Issued
April 9, 2026
Completed
Expires
October 9, 2027
106
Plan Review Days — Total
41
Plan Review Days — City Control
65
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Wallingford Neighborhood

Project Overview

Project Details
Value
$200,000
Type
Residential Construction
Issued
April 9, 2026
Location
Wallingford

Contractor Information

Contractor
FULLER LIVING CONSTRUCTION LLC
General Contractor
License FULLELC855CD

Location & Map

Project Description
Construction Permit Construct addition and substantial alterations to existing one-family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
FULLELC855CD
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1119557
Review cycles
3
Plan review days
106
Days in corrections
65
Expires
October 9, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor