PERMIT #7097920-CN
5609 BEACON AVE S, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 26, 2025
In Review
3 cycles
Reviews Done
December 31, 2025
Ready to Issue
January 5, 2026
Issued
January 8, 2026
Completed
—
Expires
July 8, 2027
66
Plan Review Days — Total
49
Plan Review Days — City Control
17
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
5609 BEACON AVE S, SEATTLE, WA Property
Other Seattle Neighborhood
Project Overview
Project Details
Value
$186,290
Type
Residential Construction
Issued
January 8, 2026
Location
Other Seattle
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
SFR Allow a new single family dwelling unit per land use code. Construct new one family dwelling and remove existing garage, maintaining two existing dwelling units, per plans
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0094835
Review cycles
3
Plan review days
66
Days in corrections
17
Expires
July 8, 2027
Existing units
1
Units added
1
Units removed
0
Sleeping rooms
0