PERMIT #7097922-GR

1423 NW MARKET ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
August 22, 2025
In Review
2 cycles
Issued
October 3, 2025
Completed
March 12, 2026
Expires
April 3, 2027
41
Plan Review Days — Total
36
Plan Review Days — City Control
5
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Ballard Neighborhood

Project Overview

Project Details
Value
$350,000
Type
Commercial Construction
Issued
October 3, 2025
Location
Ballard

Contractor Information

Contractor
JOE HALL CONSTRUCTION INC
General Contractor
License JOEHAC*259RT

Location & Map

Project Description
Safeway site # 1477 Construct alterations to replace sumps and vent pipes for existing commercial building (Safeway #1477 gas station), per plan

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
JOEHAC*259RT
Review level
Full +
Primary use
Commercial
Parcel
DV0010441
Review cycles
2
Plan review days
41
Days in corrections
5
Expires
April 3, 2027
Open official SDCI detail →