PERMIT #7098125-DM

2701 26TH AVE SW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
October 17, 2025
In Review
4 cycles
Reviews Done
March 23, 2026
Ready to Issue
March 23, 2026
Issued
April 1, 2026
Completed
Expires
October 1, 2027
157
Plan Review Days — Total
75
Plan Review Days — City Control
82
Days in Applicant Control
4
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
West Seattle Neighborhood

Project Overview

Project Details
Value
$13,000,000
Type
Industrial Construction
Issued
April 1, 2026
Location
West Seattle

Contractor Information

Contractor
SCARSELLA BROS INC
General Contractor
License SCARSBI183B8

Location & Map

Project Description
Terminal 5 Demolish existing warehouse structure (CFS building) at Terminal 5, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SCARSBI183B8
Review level
Full +
Primary use
Industrial
Parcel
DV0079997
Review cycles
4
Plan review days
157
Days in corrections
82
Expires
October 1, 2027
Open official SDCI detail →
View Contractor