PERMIT #7098243-CN
6314 7TH AVE S, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
September 16, 2025
In Review
2 cycles
Reviews Done
November 24, 2025
Ready to Issue
December 3, 2025
Issued
December 3, 2025
Completed
January 29, 2026
Expires
June 3, 2027
69
Plan Review Days — Total
54
Plan Review Days — City Control
15
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$100,000
Type
Commercial Construction
Issued
December 3, 2025
Location
Georgetown
Contractor Information
Location & Map
Project Description
Prologis Seattle 20 TI Tenant improvements for break room in existing warehouse, occupy per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
HAWKBBL824BQ
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0035257
Review cycles
2
Plan review days
69
Days in corrections
15
Expires
June 3, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0